                Home > Operational Area > TURBINE
                How to control differential expansion when turbine startup?

                The following measures can be taken according to the unit case:

                ⑴select the appropriate red switch parameters.

                ⑵develop appropriate temperature and pressure curves.

                ⑶promptly use cylinders, flanges heater for controlling the temperature difference of the metal components within a predetermined range.

                ⑷speed control increases the speed and fixed speed warm-up time, after-load, according to the master cylinder temperature rise load speed.

                ⑸timely adjustment vacuum when warming punch machines.

                ⑹Bearing seal steam supply using appropriate and timely adjustments.